Client: Neptune Developments
Value: £50 million
Architect: Falcon Chester Hall
Start Date: December 2009
Completed: December 2011
Services: Transport Planning; Civil & Structural Engineering
Read more…
8-screen cinema forming part of a large multi-purpose waterfront redevelopment. Substructure works, backfilling a 4 metre deep pit with vibro-improvement to support ground floor constructions and building frames. The cinema incorporates a steel frame structure on piled foundations, with floating floors for acoustic separation.
Key Points:
• Control of structural vibration and deflection in long span structural beams
• Construction of 750 metre long wave containment wall
• Recovery of material from marine lake bed for use as a backfill sub-base material for new car parks and roads
Close…
Client: Neptune Developments
Value: £50 million
Architect: Falcon Chester Hall
Start Date: December 2009
Completed: December 2011
Services: Transport Planning; Civil & Structural Engineering
Read more…
8-screen cinema forming part of a large multi-purpose waterfront redevelopment. Substructure works, backfilling a 4 metre deep pit with vibro-improvement to support ground floor constructions and building frames. The cinema incorporates a steel frame structure on piled foundations, with floating floors for acoustic separation.
Key Points:
• Control of structural vibration and deflection in long span structural beams
• Construction of 750 metre long wave containment wall
• Recovery of material from marine lake bed for use as a backfill sub-base material for new car parks and roads
Close…
Client-side cookies are used to verify the login status of customers using products or services linked directly with our website. Usage of a cookie is in no way linked to any personally identifiable information while on our site. If you reject the cookie, you may still use our site; however, you may not be able to access all areas of our site. Learn more.
Accept & Close